Type
Timeline
Priority
High
Requested By
Alex Rivera
2024-11-15
Assigned To
Sarah Chen
Decided 2024-11-22
Description
Additional time needed to complete data validation and rollback testing for the finance module migration.
Impact Assessment
Delays downstream integration testing by 4 weeks. No budget impact expected.