Monte Carlo Risk Distribution
Probabilistic histogram of total risk impact from Monte Carlo simulation
Export deferred
Status
24 of 28 risks included
Last run: 25 Mar 2025, 10:42 AM10,000 iterations
P10
$520K
0%
P50 (Median)
$1.2M
0%
P90
$2.5M
0%
P95
$3.1M
0%
Risk Distribution Histogram
Iterations 10,000
P10$520K
P50$1.2M
P90$2.5M
P95$3.1M
Risk Distribution Histogram — Visualization will render here
Histogram with KDE overlay in pink/purple colour scheme. X-axis: Total Impact (currency). Y-axis: Frequency. Vertical dashed lines at P10, P50, P90, P95 with currency labels.
Histogram Bins
KDE Curve
P-value Lines
Simulation Summary
| Statistic | Value |
|---|---|
| Iterations | 10,000 |
| Risks Included | 24 of 28 |
| View | Current |
| P10 | $520,000 |
| P50 (Median) | $1,240,000 |
| P90 | $2,450,000 |
| P95 | $3,100,000 |
| Distribution Range | $100,000 — $5,000,000 |
| Mean | $1,380,000 |
| Std Deviation | $620,000 |